Hoa Dong Wind Power Plant Project finished the work of pulling 110kV transmission line on 25 February 2023. This is a significant milestone for the Project to move toward the trial operation and internal grid operation, ready for the official connection and integrate into the National grid in Quarter III, 2023 as planned.

The 110kV transmission line of Hoa Dong Wind Power Plant Project has the length of 13.5 km, passing through Hoa Dong Commune, Vinh Chau Town, Soc Trang Province, managed and constructed by The Investor, Wind Power Hoa Dong Company Limited, and Project Contractors from September 2020. This is one of the special projects with the 110kV line relatively long including the connection to the line of Wind Power Project No. 18 before reaching the connection point of Vietnam Electricity Group (EVN). The project implementation process had encountered many objective factors such as COVID-19 epidemics in 2020, 2021; Especially, the long-standing problems in compensation for site clearance had caused the last pulling section to be delayed till the end of December 2022

Despite facing many difficulties, the Project had always received the attention and support of the local authorities, provincial and town Departments by removing difficulties and obstacles in the site clearance work. At the same time, the drastic intervention of the local authorities where the Project’s line goes through had created an idea condition for the construction unit to deploy and complete the project.

The completion of the 110KV transmission line means great significance to Hoa Dong Wind Power Plant Project, a premise for the trial operation of the plant and the internal grid operation, and that, to make the way to the official connection and integration to the national grid in September 2023, contributing in a clean, stable and long-term electricity supply, serving the economic development, tourism, social welfare and national security in Soc Trang Province.

Posts navigation